Case Study

Bletchley Depot (In Progress)

Client

Taylor Woodrow / WMT

GBR-Rail is contracted to Taylor Woodrow to deliver controlled emission toilet (CET) systems to West Midland Trains for their Bletchley Depot.

GBR-Rail design responsibilities of the CET system from the GRIP 4 stage up to GRIP 5 and AFC. 3D modelling forms part of these works.

CET, Sidings and Plantroom:

New EMU sidings to enable a greater number of 5 cars to be stabled at Bletchley TMD and also 2 DMU sidings to be re-modelled.

Carriage Sidings:

Existing high-level walkways to be replaced with ground level access and all associated lighting etc. CET to be upgraded to accommodate Class 730 5 car units.

Anticipated Project Completion – May 2025