Northumberland Park Main

Case Study Location: Northumberland Park Station Dates: August 24 to Sept 25 Key Deliverables: Complete Civils scope Client Morgan Sindall GBR-Price Rail Scope of Works: Full Civils build only subcontract NEC4 Option A for installation all civils infrastructure on behalf of Morgan Sindall and Northumberland County Council. Core Elements & Scope: Station Platform Works Lift […]
Farncombe to Petersfield CMS & IBJ Works

Case Study Farncombe to Petersfield CMS & IBJ Works October 2023 – Complete February 2024 | F2P Project Client Alstom Download Case Study PDF KGJ Price were contracted to provide all aspects of Permanent Way services to Alstom on the Farncombe to Petersfield Re-Signalling Project. KGJP provided a full IBJ survey […]
Barmouth Viaduct

Case Study Barmouth Viaduct – Permanent Way June 2023 – Complete December 2023 | Barmouth Viaduct Client Alun Griffiths Download Case Study PDF KGJ Price were contracted to provide Permanent Way services to Alun Griffiths to remove the existing jointed track over Barmouth Viaduct inc the Northern Approach, Assemble VIPA Baseplates and Slave Rail on the […]
Regents Canal

Case Study Regents Canal July 2022 – Complete march 2023 | Regents Canal Client Story Contracting Download Case Study PDF KGJ Price were contracted to provide all aspects of Permanent Way services to Story Contracting to remove 2076A/B crossover which was directly on top of the bridge to be replaced and supply and install a full […]
Nether Poppleton Area Resignalling

Case Study Nether Poppleton Area Resignalling July 2020 – August 2022 | Nether Poppleton Area Resignalling Client Linbrooke Services Ltd Download Case Study PDF KGJ Price Rail Ltd were awarded a package of works to supply all the labour, plant and materials to undertake all the Civils and P-Way works on Nether Poppleton Area Re-Signalling […]
Neath Swing Bridge

Case Study Neath Swingbridge March 2022 – September 2022 | Neath Swingbridge Client Centregreat Rail Download Case Study PDF KGJ Price were contracted to provide all aspects of Permanent Way services to Centregreat Rail to remove the track, ballast and re-instate the track during a series of 54 hour possessions in summer 2022. Details: Core […]
WEM Overbridge

Case Study WEM Overbridge Oct0ber 2021 – March 2022 | WEM Overbridge Client Alun Griffiths Download Case Study PDF KGJ Price were contracted to provide all aspects ofPermanent Way services to Alun Griffiths to remove thetrack, ballast and re-instate the track during a 101 hourpossession in Xmas 2021. Details: Core Elements & Scope: 542T of […]
Gipsy Patch Lane Bridge Renewal

Case Study GIPSY PATCH LANE BRIDGE RENEWAL Oct 2020 – Feb 2021 | Gipsy Patch Lane (Bristol) Client Alun Griffiths Download Case Study PDF KGJ Price were contracted to provide all aspects of Permanent Way services to Alun Griffiths Contractors to remove the track, ballast and re-instate the track fully tamped & stressed at the […]
Greater Anglia CWM Project

Case Study Greater Anglia CWM Project October 2020 – March 2021 | Greater Anglia CWM Project Client Garrandale Rail Greater Anglia Trains Download Case Study PDF KGJ Price were contracted to carry out the role of Principal Contractors for the renewal of the Carriage Wash Machine at Southend Victoria and the renewal (Bobbins and Flails) […]
Till Level Crossing Project

Case Study TILL LEVEL CROSSING PROJECT July 2020 – December 2020 | Tram Inn, Landovery and Llandrindod Wells Client Siemens Download Case Study PDF KGJ Price were contracted to provide Permanent Way Design and installation for 10 x Hollow Sleepers and 4x Pairs of IRJ’s. KGJP were then also instructed to complete the required Level […]